Automating motion trajectory Of crane-lifted loads.

Saved in:
Bibliographic Details
Title: Automating motion trajectory Of crane-lifted loads.
Authors: Olearczyk, Jacek1 jaceko@ualberta.ca, Bouferguène, Ahmed2 ahmed.bouferguene@ualberta.ca, Al-Hussein, Mohamed1 mohameda@ualberta.ca, Hermann, Ulrich (Rick)3 rhhermann@pcl.com
Source: Automation in Construction. Sep2014, Vol. 45, p178-186. 9p.
Subjects: Automation, Mobile cranes, Mechanical loads, Construction projects, Polar coordinates (Mathematics), Algorithms
Abstract: Crane Lifting Path Planning (CLPP) is an important task, especially in congested construction sites. This activity becomes extremely complex since, as the project advances, new (and sometimes unpredicted) constraints may occur. These constraints force lift engineers to explore the possibility of alternative paths for the objects still to be moved. Under severe time constraints, manual analysis of such paths is practically impossible, which makes it necessary to rely on computer implementations in order to avoid project delays. From a mathematical standpoint, if the crane payload trajectory is to be defined analytically, the polar coordinate system,( r , θ ), is naturally the most suitable. As a result, this paper proposes an algorithm for CLPP in which the path is represented as a piece-wise continuous function where each portion is defined either by constant radius (rotation of the load) or a constant angle (translation of the load). In other words, rather than forcing a crane to adapt to un-natural rectilinear trajectories as obtained by traditional path searching procedures, it is the trajectory that is adapted to the crane motion. In fact, even though (mathematically) a precise balance between the rates of rotation and translation of the jib (or boom) will make the payload follow any continuous path (regardless of its complexity), the coupling between the rotations and translations increases the difficulty of the lifting activity. However, a crane lifting path in which these motions are uncoupled will lead to less stringent requirements in terms of controlling the balance between rotations and translations. [ABSTRACT FROM AUTHOR]
Copyright of Automation in Construction is the property of Elsevier B.V. and its content may not be copied or emailed to multiple sites without the copyright holder's express written permission. Additionally, content may not be used with any artificial intelligence tools or machine learning technologies. However, users may print, download, or email articles for individual use. This abstract may be abridged. No warranty is given about the accuracy of the copy. Users should refer to the original published version of the material for the full abstract. (Copyright applies to all Abstracts.)
Database: Engineering Source
Description
Abstract:Crane Lifting Path Planning (CLPP) is an important task, especially in congested construction sites. This activity becomes extremely complex since, as the project advances, new (and sometimes unpredicted) constraints may occur. These constraints force lift engineers to explore the possibility of alternative paths for the objects still to be moved. Under severe time constraints, manual analysis of such paths is practically impossible, which makes it necessary to rely on computer implementations in order to avoid project delays. From a mathematical standpoint, if the crane payload trajectory is to be defined analytically, the polar coordinate system,( r , θ ), is naturally the most suitable. As a result, this paper proposes an algorithm for CLPP in which the path is represented as a piece-wise continuous function where each portion is defined either by constant radius (rotation of the load) or a constant angle (translation of the load). In other words, rather than forcing a crane to adapt to un-natural rectilinear trajectories as obtained by traditional path searching procedures, it is the trajectory that is adapted to the crane motion. In fact, even though (mathematically) a precise balance between the rates of rotation and translation of the jib (or boom) will make the payload follow any continuous path (regardless of its complexity), the coupling between the rotations and translations increases the difficulty of the lifting activity. However, a crane lifting path in which these motions are uncoupled will lead to less stringent requirements in terms of controlling the balance between rotations and translations. [ABSTRACT FROM AUTHOR]
ISSN:09265805
DOI:10.1016/j.autcon.2014.06.001